Week 4
Overview of Activities Group Meeting As usual, we held a group meeting on Wednesday, one day before our last lab session on Thursday. Knowing that our Bench Inspection would be on next week's Thursday, we were under pressure to ensure that we completed all the actual lab work this week, though we had the option to take some extra lab time on Friday if we really needed to. Thus, we discussed our progress on the project so far and what we would need to do the next day. We also went over the materials that we would need for the Bench Inspection, checked our progress, and revised who was responsible for what. During the meeting itself, we worked on our individual log books, and updated our group's role allocation and contribution to project deliverables forms. Lab Day Some group members worked on the project's exterior, trying to make it look more presentable. They were able to cover all the sides of the cardboard box with thin black sheets which made it look much neater. Wel...